In 2008, Taseko Mines Limited engaged Allnorth as part of a team to undertake a feasibility study on the Prosperity Mine. Allnorth worked with the Taseko team to prepare a NI 43-101 compliant technical report for the 70,000 tons per day copper-gold mine near Williams Lake, BC.

Allnorth’s responsibilities included the design of the process plant, camp facilities, and crushing, stockpiling and conveying systems. As part of the design effort Allnorth also designed a nine-bay truck shop with light vehicle shop, heated and cold storage warehouse and a separate wash bay.

Allnorth also prepared capital cost estimates for all areas of responsibility and wrote the report narratives for the appropriate report sections in the technical report.

In 2010, Taseko Mines once again engaged Allnorth to be part of a team to prepare a gap analysis report, updating the CAPEX (capital cost estimate) and designs to incorporate any changes that had occurred  since the last report.

Responsibilities

  • Mechanical, structural, civil design
  • Report preparation
  • Capital cost estimating
  • Procurement

Location

Williams Lake, BC

Connect With Our Team

With locations across Canada and the United States, Allnorth works closely with clients to deliver practical solutions tailored to their unique goals and challenges. Our local teams are backed by specialists from across the company, giving you access to the right expertise when and where it's needed most.

Start a conversation with our team and discover what's possible.

Contact Us