Allnorth has expanded its ICE service offerings with the acquisition of Dynamysk Automation Ltd. in 2024. The following is a demonstration of the bench strength added to our team.
Overview
The client operates several pipelines. Most of these are in northern Alberta, with some extended through Saskatchewan into North Dakota and into eastern USA. The client purchased pipeline where our company was already in place as the primary automation contractor. With our experience and developing working relationship, the client continued to utilize our expertise on these pipelines.
Our Role
With site experience dating back to 2006, Dynamysk was initially working on Maintenance and Engineering projects for the Alberta Ethane Gathering System pipeline, and then another cross- border ethane pipeline that feeds into it, from 2013.
Our responsibilities include detailed instrumentation, control and electrical engineering (ICE), project management for ICE and multidiscipline projects, along with day-to-day maintenance and troubleshooting of problems that arise. Dynamysk’s knowledge of the sites allow for quick solutions.
Field Services
The Field Services team also has a presence at the client’s facilities. We supply Instrumentation and Electrical Maintenance personnel and turnaround crews, as well as construction and commissioning support.
Field Services has been involved on multiple projects including Maintenance, Turnarounds, Commissioning, Shutdowns and more.
Engineering Project Statistics
Program Duration: 8+ years
Projects Executed: 30+
Staffing Levels: 10 engineering, 5 field services
Hardware Vendors: Rockwell Automation, Schneider
Process Safety: Area Classification
Instrumentation: Specifications /Procurement
Control: PLC, Communications
Electrical: MCC, UPS, CFD, Cabinets
Drawings & Datasheets: AutoCAD
Engineering Project Success Criteria
Project Resources
Allows client to focus on other priorities with Dynamysk handling the details.
Project Execution
Enabled client to successfully execute more projects than they could in-house.
Cost Savings
Project savings realized by using Dynamysk over incumbent vendors.
Service and Support
Dedicated team to ensure cost effective and responsive support.
Field Services Success Criteria
Cost Savings
Integrated engineering and panel design groups to reduce design costs.