The Red Chris property is a copper-gold mine commissioned in 2015 and located in northern British Columbia. This open pit mine uses a conventional 30,000 tpd milling operation, and tailings impoundment to produce a Cu-Au bearing concentrate which is shipped to third party smelters. Allnorth was retained by Newcrest – Red Chris JV to provide engineering services and record drawings for the process plant. Allnorth’s scope of work included:
- Site field verifications
- Updated Process Flow Diagrams (PFD’s)
- Updated Piping & Instrumentation Diagrams (P&ID’s)
Allnorth’s final deliverable included a package of approximately 40 record drawings that was used by our team as a basis for the Red Chris Mine Cleaner Circuit Design Project.
RESPONSIBILITIES:
- Process Flow Diagram (PFD) Updates
- Piping & Instrumentation Diagram (P&ID) Updates
LOCATION
Dease Lake, BC