Mine Powerline - Mt. Milligan

The scope of work for the Project consisted of preparing and submitting all applications for regulatory approval to construct a 92km long power line from BC Hydro’s Kennedy substation to the proposed Mt. Milligan open-pit gold-copper mine located near Fort St.James, BC.

Client: Terrane Metals Corporation

Responsibilities:

  • License of Occupation
  • Occupant License to Cut
  • RTK GPS Survey
  • Engineered Cost Estimates
  • Comprehensive base map review
  • Detailed field assessment
  • Close coordination with consulting groups and government agencies

Project Location: Fort St. James, BC

Project Delivery: 2010

Project Costs: $917,000,000