Kutcho Creek Mine Access Road

The scope of work for the Kutcho Creek Mine consisted of the layout, survey and design of a 123km access road, with associated bridges and culverts, from Dease Lake, BC, to the mine site. A comprehensive access management plan was completed to determine the most economical and feasible means of accessing the remote mine site. Other works included; a fish compensation stream survey, a drill collar survey and the establishment of geodetic control.

Client: Western Keltic – Sherwood Copper – Capstone Mining

Responsibilities:

  • Project Management
  • Assessed road development potential
  • RTK GPS Survey
  • Engineering Cost Estimates
  • Base map acquisition, amalgamation and comprehensive review
  • Detailed field assessment
  • Identification of stream crossings along corridor
  • Review of EA application
  • Close coordination with consulting groups and governement agencies

Project Location: Dease Lake, BC

Project Delivery: December 2008

Project Cost: $350 Million